| Design Process |
100% |
| Construction Process |
100% |
| BREEAM Rating and score |
Target = Very Good, Score = TBC |
| Basic Building Cost - £/m2 |
- £/m2 |
| Services Costs - £/m2 |
- £/m2 |
| External Works - £/m2 |
- £/m2 |
| Gross floor area - m2 |
Primary 2,455m2 and Nursery 287m2 |
| Total area of site - hectares |
2.2 hectare |
| Function areas and their size (m2) |
Teaching 277m2 |
| Area of circulation (m2) |
203m2 |
| Area of storage (m2) |
165 m2 |
| % area of grounds to be used by community (where relevant) |
50% |
| % area of buildings to be used by community (where relevant) |
80% |
| Predicted electricity consumption - kWh/m2 |
25 kWh/m2 |
| Predicted fossil fuel consumption - kWh/m2 |
125 kWh/m2 |
| Predicted renewable energy generation - kWh/m2 |
0.06 kWh/m2 |
| Predicted water use - m3/person/year |
4 m3/person/year |
| % predicted water use to be provided by rainwater or greywater |
Not Applicable |
| The steps taken during the construction process to reduce environmental impacts |
Site Waste Management Plans are used on all projects and we use Smart Waste as its main tool for monitoring and managing all waste management activities. |
| Innovative construction management techniques |
Strategic Partnering allowed us to form an Integrated Design Team at a very beginning of the design process. Bringing all of the key stakeholders together resulted in designs which were optimised to meet aspirations as well as provide value for money. |
| A list of any social or economically sustainable measures achieved/piloted. |
The site was registered with the Considerate Constructors scheme.
As part of our commitment to social sustainability we worked closely with local residents committees to ensure that disruption due to construction activities was kept to a minimum. Our regular newsletters provided the community with updates on the progress of construction
|